PROJECT BACKGROUND:

  • Mumbai Metropolitan Regional Development Authority (MMRDA) has undertaken construction of underground road connectivity from Orange Gate to Marine Drive at Mumbai Island city, to meet the growing traffic demand and improvement of transportation scenario in Mumbai Metropolitan Area.
  • MMRDA had appointed M/s. PADECO Co. Ltd as a consultant for preparation of a Detailed Project Report (DPR). Accordingly, the consultant has prepared and submitted the DPR on 14.06.2023.
  • The Administrative approval to project cost amounting to Rs. 8,056 Crore is granted in 154th Authority meeting held on 10th March 2023.
  • The foundation stone for this project was laid by the Hon’ble Prime Minister of India on 12th January 2024.

PROJECT DESCRIPTION

  • The Eastern Freeway terminates at Orange Gate of MbPT at P’DeMello road. The traffic merges with existing traffic on P’DeMello road. This creates traffic congestion and queuing on up as well as down ramps during peak hours. Government Post Office junction is affected and signal time for the commuters increased substantially. This project will serve as a crucial link connecting the heavily congested urban area of Mumbai, facilitating an east-west coastal connection through the Eastern Expressway to the Marine Drive, and providing a fast and efficient traffic system
  • The project alignment crosses Harbour Line alignment (Central Railway) near Old Elphinstone Bridge, Western Railway near Charni Road Station, proposed Metro Line 11 & Metro Line 3 near Lamington Road Junction and ends near Bal Bhavan on Netaji Subhash Chandra Bose Road at Marine Drive.
  • The Project will help in reduction of travel time and lead to fuel savings. About 14650 vehicles are estimated to travel daily on Orange Gate tunnel project in horizon year 2029.
  • The project consists of underground tunnels to be constructed by using 2 numbers of Tunnel Boring Machines (TBM). Project also consist of cut & cover and open ramp on both sides and elevated down ramp from Eastern Free Way.
  • The inner diameter of each tunnel is 11 meters and outer diameter is 12.30 meters.
  • Each tunnel shall have 2 lanes of 3.2 m width, 1 emergency lane & raised foot path    (0.6 m) with design speed of 80 km/hr.
  • Total project length considering both tunnels is 4.9 Kms (including Cut and Cover and Ramps) which includes 3.71 Kms of LHS tunnel and 3.73 Kms of RHS tunnel. Total Tunnel length using tunnel boring machine is 7.44 Kms.
  • The maximum depth of the crown of the tunnel is about 52 m from the ground maintaining safe clearance with the MML3, Central Rail, Western Rail, high-rise building foundations and other existing buildings and structures.
  • Tunnels will have inner reinforced concrete precast linings segments for structural stability, durability as well as construction of cross passages etc.
  • Minimum vertical clearance of 5.50 m is being provided over the full width of carriageway and Emergency Lane.
  • Additional vertical clearance is being provided for accommodating tunnel lighting fixtures and other accessories.
  • The carriageways inside the tunnels will be of cement concrete.
  • To ensure proper ventilation within the tunnels, necessary mechanization is proposed. Fire-resistant systems, adequate lighting, and an Intelligent Transport System (ITS) for efficient traffic management are among the various planned features.
  • The expected construction period is 54 months.
  • The project is funded by loan from Union Bank of India.

 

PRESENT STATUS:

  • M/s. Larsen & Toubro Construction has been awarded construction of the project on ‘Design & Build’ basis vide Notice to Proceed dated 20.06.2024.
  • M/s. Hill International- Tata Consulting Engineers JV has been awarded the contract for Project Management Consultancy vide Notice to Proceed dated 20.06.2024.
  • Majority of necessary permissions from concerned authorities have been received and others are in advanced stage of issuance.
  • 1.96 Ha land has been handed over by MbPA on 1st October’ 2024 after intervention of Hon’ble Chief Minister, Maharashtra and the launching shaft works commenced thereafter.
  • The refurbishment of one Tunnel Boring Machine along with the Tunnel Boring Machine Launching Shaft construction at Eastern Water Front Area is completed.
  • The Launching Ceremony was held on 03.12.2025 by august hands of Hon’ble CM of Maharashtra.
  • The FAT and SAT of the TBM were successfully conducted below Launching Shaft area.
  • The mining of the South Bound Tunnel (SBT) has commenced and progress has crossed 1000 m.
  • Physical Progress of the project: 33.27 % (Till September 2026)
  • Financial Progress of the project: 27.04 % (Till September 2026)
Orange Gate to Marine Drive Tunnel Project - Others
S. No. Title Download
1 Project Alignment- Orange Gate to Marine Drive Tunnel Project Download (4.26 MB)Project Alignment- Orange Gate to Marine Drive Tunnel Project
Orange Gate to Marine Drive Tunnel Project - Others
S. No. Title Download
1 AA Download (2.21 MB)AA
2 Work Order for Ms. PADECO Download (309.04 KB)Work Order for Ms. PADECO
3 Letter of Acceptance to Ms. L&T Download (81.83 KB)Letter of Acceptance to Ms. L&T
4 Contract Agreement of Ms. L&T Download (2.34 MB)Contract Agreement of Ms. L&T
5 Letter of Acceptance of Ms. Hill-TCE (JV) Download (1.19 MB) Letter of Acceptance of Ms. Hill-TCE (JV)
6 contract a Download (3.99 MB) contract a
7 Notice to proceed from MMRDA to Ms. L&T Download (82.04 KB) Notice to proceed from MMRDA to Ms. L&T
8 Notice to proceed from MMRDA to Ms. Hill-TCE (JV) Download (112.98 KB)Notice to proceed from MMRDA to Ms. Hill-TCE (JV)
9 CRZ approval granted by MCZMA in its 171st meeting. Download (2.24 MB)CRZ approval granted by MCZMA in its 171st meeting.
10 Msrdc in principal noc pdf Download (521.49 KB)Msrdc in principal noc pdf
11 Mumbai Port Authority In-principle NOC. Download (496.55 KB) Mumbai Port Authority In-principle NOC.
12 Joint CP (Traffic) In- principal NOC. Download (332.8 KB)Joint CP (Traffic) In- principal NOC.
13 MCZMA NOC 198th MoM Download (5.07 MB)MCZMA NOC 198th MoM
14 MSRDC-Final NOC Download (1.31 MB)MSRDC-Final NOC
15 Orange Gate Gr Dated Download (235.04 KB)Orange Gate Gr Dated
16 PMC NTP WO Letter No.773 Download (112.98 KB)PMC NTP WO Letter No.773
17 Traffic Police NOC Download (1.27 MB)Traffic Police NOC
18 Work Order PADECO dated 15.11.2022 Download (309.04 KB)Work Order PADECO dated 15.11.2022
19 Central Railway NOC Download (370.61 KB)Central Railway NOC
20 Coastal Road_BMC_In principle NOC for Option E Download (178.78 KB)Coastal Road_BMC_In principle NOC for Option E
21 Contract agreement Hill Download (3.99 MB)Contract agreement Hill
22 Contract Agreement Download (2.34 MB)Contract Agreement
23 Contractor NTP WO LEtter No. 772 Download (82.04 KB)Contractor NTP WO LEtter No. 772
24 CRZ clearance-Orange gate tunnel road 01.07.2026 Download (1.2 MB)CRZ clearance-Orange gate tunnel road 01.07.2026
25 GR dated 12.08.2025_Finance SASCI 2025-26 Rs.132 Cr Download (379.89 KB)GR  dated 12.08.2025_Finance SASCI 2025-26 Rs.132 Cr
26 GR dated 07.10.2024 ऑरंज गेट ते मरीन ड्राईव्ह भुयारी मार्ग Download (191.71 KB)GR dated 07.10.2024 ऑरंज गेट ते मरीन ड्राईव्ह  भुयारी मार्ग
27 GR dated 26.12.2025_Finance SASCI 2025-26 Rs.68 Cr Download (404.18 KB)GR dated 26.12.2025_Finance SASCI 2025-26 Rs.68 Cr
28 LOA PMC Download (1.19 MB)LOA PMC
29 LOA-L&T Download (87.88 KB)LOA-L&T
30 MbPA_In-Principle-NOC_09-01-2024 Download (496.55 KB)MbPA_In-Principle-NOC_09-01-2024
31 154th_Authority Meeting_dated_24.03.2023_MOM_dated_10.03.2023_Regarding Giving Administrative sanction to the work Download (249.81 KB)154th_Authority Meeting_dated_24.03.2023_MOM_dated_10.03.2023_Regarding Giving Administrative sanction to the work
32 272nd_Executive Committee Meeting dated_01_11_2022 & MOM dated 21_10_2022 Download (183.89 KB)272nd_Executive Committee Meeting dated_01_11_2022 & MOM dated 21_10_2022
33 276 EC Download (5.71 MB)276 EC
34 277 EC Download (6.15 MB)277 EC
35 AA for appointment Download (2.21 MB)AA for appointment
×