inner-banner

Metro Line - 12

  • Metro Line 12 connection through Kalyan, Dombivali MIDC, Kalyan Growth Centre, Wadavli, Turbhe, Pisarve, Taloja and Amandoot.
  • Dedicated Depot is planned at Nilje in up to an extent of 31 Ha.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
  • It shall provide rail-based access to the commercial, Govt. bodies and geographical landmarks in Mumbai & Navi Mumbai.

 

  • Length: 23.57 Km (Fully Elevated)
  • Line Color: Orange Line
  • Stations: 19 Nos. (Fully Elevated)
  • Depot: Nilje (31 Ha.)
  • Interchanging Stations:
    • Kalyan (Metro Line 5: Thane-Bhiwandi-Kalyan)
    • Hedutane (Metro Line 14: Vikroli-Badlapur)
    • Amandoot (Navi Mumbai Metro Line 1)
  • Project Completion Cost: ₹ 5,865 Cr.
  • Daily Ridership (2031): 2.62 Lakhs
Sr. No. Name of Work Status (%)
1 Pile Works 19%
2 Pile Cap Works 14%
3 Pier Works 7%
4 Pier Cap Works (Erection) 5%
5 U Girder Works (Erection) 0.5%
P129 to P138 , P125 to P128 , P630 to 637 , P653 to P658 , U Girder Casting Work at Mangaon Casting Yard , Pier cap Casting Work at Mangaon Casting Yard