Sr. No. Name of Work Status
1 Pile Cap Works 97% completed
2 Pier Works 95.07% completed
3 Pier Cap Works (Erection) 94% completed
4 Flyover Pier Cap 99.00% Casting completed
99.00% Erection completed
5 U-Girder Works 96.00% Casting completed
93.50% Erection completed
6 Station Works 79.63% completed
7 Station Entry–Exit Works 38.50% completed